Industry: Education
Neoga CUSD 3 – High School & Elementary Renovations
- Location: Neoga, IL
- Design Team: Upchurch and Associates
- Service Provided: General Contracting
Project Overview
This project was delivered in two summer-phase sequences. Phase 1 included roof membrane replacement, precast panel sealing and painting, floor tile abatement, flooring and ceiling replacement, selective demolition, science lab renovations, MEP upgrades, and full reconstruction of four restrooms. Phase 2 included a 3,300 SF weight room addition, further abatement, complete demolition and reconstruction of locker room and restroom areas, and updated finishes, casework, and flooring across additional school spaces.